Production timeline
January 2008: Initial testing of low volume pre-production HPP engine
- April 2008: Sentec production design of electronics and power controls commences
- May 2008: Enertek commence boiler build out and burner commercialisation of the HPP
- June 2008: Low volume production engine endurance testing to commence
- September 2008: Initial prodcution process to commence with assembly / production / manufacturing with sub contractors Autocraft and Malvern Boilers, producing first commercial HomePowerPlant appliances for UK and EU field trials by utilities
- October 2008: Expansion of component supply chain to middle and far east
- Feb- March 2009: Commercial production for UK, EU and North America begins
|