Production timeline

  • January 2008: Initial testing of low volume pre-production HPP engine
  • April 2008: Sentec production design of electronics and power controls commences
  • May 2008: Enertek commence boiler build out and burner commercialisation of the HPP
  • November 2009: Low volume production engine endurance testing to commence
  • Q2 2010 (funding dependant): Initial production process to commence with assembly / production / manufacturing with sub contractors Autocraft and Malvern Boilers, producing first commercial HomePowerPlant appliances for UK and EU field trials by utilities